The Six Links: Where Extension of Time Packages Disintegrate

Published: 2025-10-22·4 min read·First posted on LinkedIn on 22 October 2025
01 / THE SITUATION

Reviewing a 1,200-page claim bundle submitted by an international EPC joint venture. Massive appendices, beautifully bound charts, drone photographs of idle cranes. Total sum demanded: US$ 38m.

(- A pile of invoices is not a quantum claim. It is just proof that money was spent somewhere.)
02 / THE RULE THAT APPLIES

A claim is a chain of six unbroken links: 1) Event occurred, 2) Employer contractual responsibility, 3) Compliant notice served, 4) Physical impact on works, 5) Critical path affected in the accepted schedule, and 6) Actual substantiated cost incurred.

03 / THE CONSEQUENCE

The bundle had 800 pages on Link 1 (event) and 300 pages on Link 6 (invoices). Links 3, 4 and 5 were covered by three speculative paragraphs.

04 / PRACTICE POSITION

Break one link and the chain fails. We do not write 1,200-page narratives to conceal weak links. We test all six links before serving. If Link 3 or Link 5 does not hold, we tell you on day 14, before you pay six-figure consulting fees on an illusion.