Contract Musings

The formal contracts and claims register. Short situation, the rule that applies, the consequence, and the firm position. Never mixed with Capital Projects.

Filter Topics:
#ContractMusing#CaseStudy#LongstopLetter#ExtensionOfTime#Termination#Concurrency#TimeBars2026-11-22 · 7 min interactive case study

The Longstop Letter: A Fictional Case Study in Delay, Notice and Termination

The Situation:An employer is building an iron ore concentrator, Phase 2, in Veldora under a lump-sum EPC contract with Completion Dates and Longstop Dates. A 4-month employer site handover delay and contractor welder shortage run concurrently on the tailings plant.

(- The late notice did not create the delay, but it removed the contractor's best argument.)

First posted on LinkedIn: 22 November 2026Read full analysis & rule
#ContractMusing#EoTReadiness#DecisionLedger#GateReview#DelayForensics#RiskSeverity2026-08-15 · 9 min interactive review

Application Readiness Review: Contractor's Extension of Time (EoT)

The Situation:Contractor's multi-million dollar Extension of Time (EoT) Application across Onshore and Offshore contracts on an integrated infrastructure megaproject, with a target issue date of T (11 working days).

(- Meeting target date T is a resourcing and strategy decision before it is a legal one.)

First posted on LinkedIn: 15 August 2026Read full analysis & rule
#ContractMusing#TimeBars#FIDIC#ConstructionDisputes2026-02-28 · 4 min read

The Claim Does Not Fail on the Merits. It Fails at the Gate.

The Situation:A contractor completes 18 complex site variations over fourteen months. The works were genuinely instructed by the engineer. The additional plant and overtime were spent. The physical delay to commissioning is beyond dispute.

(- You can argue prevention principle all the way to London or Dubai Court. The tribunal will still read the 28-day notice clause first.)

First posted on LinkedIn: 28 February 2026Read full analysis & rule
#ContractMusing#ExtensionOfTime#DelayAnalysis#RecordsDiscipline2026-01-18 · 3 min read

Delay Is a Fact. Entitlement Is a Document.

The Situation:A project manager stands in front of his board: "The employer delayed our heavy lift by 68 days. Everyone knows it. The client’s representative was on site every morning nodding his head."

(- The client representative who nodded on site has usually been reassigned to another country by the time the claim is heard.)

First posted on LinkedIn: 18 January 2026Read full analysis & rule
#ContractMusing#Concurrency#ExtensionOfTime#Prolongation2025-12-05 · 5 min read

Concurrent Delay: The Great Contractor Refuge

The Situation:The employer fails to release the civil foundations for Area 3 on date X. The contractor claims 45 days EoT and full prolongation costs. The employer’s defence discovers the contractor had not even placed the purchase order for the structural steelwork due in Area 3 until six weeks later.

(- The fastest way to lose an entire claim is to let the opposing delay analyst find your unprocured equipment before you disclose it.)

First posted on LinkedIn: 05 December 2025Read full analysis & rule
#ContractMusing#ForensicDelay#Quantum#ClaimsMethodology2025-10-22 · 4 min read

The Six Links: Where Extension of Time Packages Disintegrate

The Situation:Reviewing a 1,200-page claim bundle submitted by an international EPC joint venture. Massive appendices, beautifully bound charts, drone photographs of idle cranes. Total sum demanded: US$ 38m.

(- A pile of invoices is not a quantum claim. It is just proof that money was spent somewhere.)

First posted on LinkedIn: 22 October 2025Read full analysis & rule