The Longstop Letter: A Fictional Case Study in Delay, Notice and Termination
The Situation:An employer is building an iron ore concentrator, Phase 2, in Veldora under a lump-sum EPC contract with Completion Dates and Longstop Dates. A 4-month employer site handover delay and contractor welder shortage run concurrently on the tailings plant.
(- The late notice did not create the delay, but it removed the contractor's best argument.)