DOOR 1 · CAPITAL PROJECTS

Know your risk before the final decision.

We look for the risk before it reaches the budget. Independent, senior-led development advice, from first screening to final investment decision.

Development advisory focus: We advise on what a board, an investment committee, or an infrastructure lender will test. We do not arrange finance or solicit funds.

EMPIRICAL REFERENCE-CLASS DATA

Overrun is the central case.

When capital forecasts rely solely on bottom-up engineering assumptions, they carry systemic optimism bias. In the empirical record, cost overrun is not an aberration; it is the default outcome across energy and civil infrastructure.

REFERENCE-CLASS BENCHMARKING

Cost Overrun Risk Across Energy & Infrastructure Classes

17 asset classes benchmarked against actual outturn capital expenditure across 16,000+ projects globally.

Click column headers to sort
Class
N
Average Cost Overrun %
% of Projects Overrunning >50%
Nuclear storage(N = 25)HIGHEST IN CLASSsmall sample— Covers nuclear waste storage
25+233%52.00%
Nuclear power(N = 196)
196+120%54.59%
Hydroelectric dams(N = 300)
300+75%37.33%
IT(N = 5360)
5360+73%18.26%
Rail stations(N = 71)small sample
71+43%23.94%
Rail(N = 372)
372+39%27.15%
Tunnels(N = 69)small sample
69+36%27.54%
Oil and gas(N = 116)
116+31%19.83%
Mining(N = 886)
886+27%16.93%
Bridges(N = 61)small sample
61+26%21.31%
Water(N = 265)
265+20%13.21%
Fossil thermal power(N = 136)
136+18%15.44%
Your Project?Which asset class or sector is your capital programme in?
Roads(N = 2086)
2086+15%9.97%
Pipelines(N = 437)
437+14%9.61%
Wind power(N = 84)small sample
84+12%7.14%
Electricity transmission(N = 50)small sample
50+8%4.00%
Solar power(N = 41)small sample
41+1%2.44%
Highest Risk Classes: Nuclear Storage & Nuclear Power

Nuclear Storage (Avg Overrun)

+233%

Highest in class (N = 25, small sample). Covers nuclear waste storage.

Nuclear Storage (>50% Overrun)

52.00%

Share of projects overrunning by more than 50%.

Nuclear Power (Avg Overrun)

+120%

Average cost overrun across N = 196 completed nuclear power projects.

Nuclear Power (>50% Overrun)

54.59%

54.59% of nuclear power projects exceed sanction budget by >50%.

Source: Flyvbjerg, B., Budzier, A. and Christodoulou, M., "Towards a Theory of Modular Natives: Explaining Superscaling, China's Greatest Innovation Yet", arXiv:2606.15757, Draft 4.2, Table 1. Real terms, measured from final investment decision. Cost analysis N = 11,011 projects, from a database of 16,000+ projects across 23 project types. Accessed 24 Nov 2026.

Footnote: A working paper. Check the final published version before relying on exact values.
THE ROADMAP TO SANCTION

The Path to the Final Investment Decision

Seven sequential evaluation gates to stress-test the project before balance-sheet exposure is committed.

01Stage

Development Planning

What is the commercial mandate, boundary conditions, and preliminary charter?

02Stage

Concept Design

Which technology pathways, site options, and modular boundaries are viable?

03Stage

Screening

What physical, regulatory, supply-chain, or grid constraints kill the project early?

04Stage

Risk Assessment

How do reference-class distributions challenge our optimistic base estimate?

05Stage

Selection

Which consortium partners, licensors, and SPV structures withstand bank scrutiny?

06Stage

Pre-FEED

Are design packages sufficiently frozen to invite competitive pricing without scope creep?

07Stage

FID Readiness

Is the decision file complete, contingency tiered, and governance signed off?

Handover Marker:FEED and award: seamless handover to Project Management Services for contract administration & controls.
“We advise on what a board or a lender will test. We do not arrange it.”
METHODOLOGY

Our edge: three methods.

Adapted from empirical megaproject research (Flyvbjerg and Gardner, How Big Things Get Done). We replace wishful bottom-up scheduling with reference-class evidence, multi-tiered contingency, and modular industrial delivery.

METHOD 01 · REFERENCE-CLASS BENCHMARKING

“Know your risk before FID.”

Estimates set against empirical reference-class data: your own past projects, your direct peers, and analogous industrial sectors. Benchmarks reveal your true statistical uncertainty, identify tail risks that internal cost models conceal, and make baseline sanction estimates resilient to project reality.

Deliverable: Empirical probability distribution (P50, P80, P90) · Not a fragile single-point estimate.
METHOD 02 · SAFEGUARD CONTINGENCY

Contingency that Survives Scrutiny

Realistic megaproject contingency is substantially larger than boardrooms expect. A tiered regime lets each party hold the risk it can afford.

Tier 3 · Portfolio Reserve
Held by Programme Owner / Board

Conservative Tail-Risk Reserve

Reserved exclusively at the portfolio or sponsor level. Intended for unhedged macro shifts, extreme geopolitical/regulatory delays, and catastrophic black swan occurrences. Never disclosed to contractors or individual package managers to avoid Parkinson's Law expenditure.

Tier 2 · Project Baseline Contingency
Managed by Project Director

Expected Value Contingency (P50/P80)

Derived from reference-class empirical benchmarks. Allocates quantified budget and schedule float for anticipated design iterations, known subsurface variances, and normal vendor lead-time adjustments. Released only via formal Change Control Board approval.

Tier 1 · Package Target Contingency
Allocated on Pain-and-Gain Terms

Ambitious Performance Targets

Target schedule and budget figures passed to EPC contractors and trade package suppliers. Structured under aligned target cost mechanisms where contractor margin expands for early completion and decreases for avoidable schedule slippage.

Reference: Bent Flyvbjerg and Dan Gardner, How Big Things Get Done. We design the tiered contingency regime to fit your risk appetite, your ambition, and what your balance sheet can realistically afford.

METHOD 03 · SMART SCALING

Built for Modularity: The 2×2 Pace vs Design Matrix

After Flyvbjerg & Gardner (*How Big Things Get Done*). Click a quadrant to examine industrial delivery dynamics.

Modular & FastSuccess & Compounding Learning

Smart Scaling

Standardised designs fabricated in high-productivity factory environments, transported as modules, and rapidly assembled on site. Captures economies of repetition and rapid learning curve reductions.

“The core industrial logic favouring SMR reactor fleets over one-off gigawatt builds.”

Bespoke & FastLow Quality & Hidden Defects

Forced Scaling

Rushing field construction before design packages and drawings are frozen. Leads to massive engineering churn, field rework, cut cables, and destructive delay claims.

“Fast on paper, catastrophic on site.”

Modular & SlowMissed Opportunity & Diluted Advantage

Fumbled Scaling

Factory-built components sitting in storage yards while regulatory approvals or local permits stall. The capital cost of idling offsets manufacturing savings.

“Good technology held back by weak regulatory and interface management.”

Bespoke & SlowBoondoggle & Chronic Overrun

Dumb Scaling

Every plant redesigned from scratch on site. No two valves or pipes identical. Zero institutional learning transferred. The classic multi-billion megaproject trap.

“The default outcome of bespoke FOAK gigawatt nuclear.”

Practice View: Modular programmes capture economies of learning, which is the foundational engineering and commercial logic that should favour SMR fleets over one-off bespoke reactors.

DEVELOPMENT ADVISORY SCOPE

What we do.

Senior advisory across four distinct pre-sanction mandates:

01 / CONCEPT TO FID

Concept-to-FID Development Advisory

Project charter, screening, site selection, pre-FEED management, and FID readiness protocols. Partner selection and SPV commercial structuring (joint-venture agreements, licensor interface boundaries, and allocation of key commercial liabilities).

What you get: An independent FID Readiness Dossier and the open decisions list with named accountability.
02 / BENCHMARK & STRESS-TEST

Benchmark & Stress-Test

Base capital cost estimates and baseline CPM schedule logic set against empirical reference-class datasets. Stress-testing contractor market capacity, lead times on ultra-heavy forgings, and vendor availability.

What you get: A validated outturn capital range with confidence intervals, not a fragile single-point number.
03 / SAFEGUARD CONTINGENCY

Safeguard Contingency Design

Architecting multi-tier contingency structures separating portfolio tail reserves from package target budgets. Aligns incentives between sponsors, lenders, and EPC consortiums under pain-and-gain governance.

What you get: A tiered governance protocol that prevents premature contingency bleed.
04 / INDUSTRIAL DELIVERY

Smart Scaling & Industrial Delivery

Evaluation of modularisation strategies versus on-site civil fabrication. Assessing whether qualified fabricators, heavy-lift vessels, and licensed engineering manpower exist to build at planned pace without bottlenecking.

What you get: A supply-chain constraint map and module fabrication schedule.
SECTOR COVERAGE

Where we work.

We advise on complex, capital-intensive infrastructure where mistakes before FID compound exponentially:

Refining & Petrochemicals

Cracker units, revamps, aromatics expansions

LNG & Gas-Power

Liquefaction, regasification, combined cycle

Utility-Scale Solar

100 MW+ PV installations, transmission interfaces

Ports & Marine

Deepwater berths, breakwaters, bulk terminals

Mining Infrastructure

Heavy rail links, mineral processing, tailings

Nuclear & SMR

We write about it, and we would welcome advisory work.

DIRECTOR TRACK RECORD

Experience of our Director.

Note on attribution: The matters below reflect the individual executive track record of our Director across past corporate leadership appointments, presented in an advisory capacity and strictly anonymised for client privilege.

Executive Leadership (Past Tense)

Chief Operating Officer, Energy & Infrastructure Group (2021–2024)

Led pre-FID development, consortium screening, and non-recourse project finance documentation across a multi-billion dollar international capital portfolio. Structured joint ventures, special-purpose vehicles (SPVs), and negotiated principal licensor agreements.

Owner-Side Programme Advisory

US$ 24bn Mining & Infrastructure Programme, West Africa

Sat owner-side as principal commercial advisor on an integrated megaproject comprising open-pit iron ore mines, multi-hundred kilometre heavy-haul rail infrastructure, and dedicated deepwater marine export facilities.

Debt Restructuring Leadership

US$ 717m Loan Facility Restructuring

Directed debt restructuring and covenant renegotiation for an operating industrial complex on a severely compressed timeline, preserving balance-sheet solvency and operational continuity across international banking syndicates.

Procurement & Tendering

Pre-Award Packages Taken to Award: ~US$ 2.4bn

Formulated tender architecture, evaluation criteria, and contract conditions for major turnkey EPC and EPCM packages, de-risking interfaces and ambiguity before binding commercial award.

THE CAPITAL-PROJECTS JOURNAL

Nuclear Post

Disciplined delivery research on advanced nuclear and megaproject capital allocation. Every figure traces to primary sources. No claims vocabulary.

FLEET SCALE & DELIVERY RATE2026-11-18

A Speed, Not a Stock: 100 GW by 2047 as a Delivery Rate

The official roadmap expects about 22 GW of nuclear capacity by 2031–32 and aims for 100 GW by 2047. That is 78 GW to add in roughly 15 years, or about 5.2 GW a year. Capacity installed since October 1969 is about 8.8 GW, a pace well under 0.2 GW a year.

5.2 GW/yrAverage annual addition from about 22 GW in 2031–32 to 100 GW in 2047
7 min readRead post →
PROCUREMENT & MARKET STRUCTURE2026-03-15

One Bidder: Why Competitive Tendering Fails in Advanced Nuclear

When a capital programme requires five years of pre-investment screening and billions in licensed design commitments, standard competitive auctions collapse to single-vendor bilateral lock-ins.

1 of 4Shortlisted vendors reaching binding final pricing in contested SMR programmes